Current Status |
|||||
| Report Name | Change Summary |
Effective Date |
Description |
Template |
Sample |
| sp_projectedshareicr | Modified. Section "Capacity Zone" new column "Capacity Zone Peak Contributions". The first version of this report may be released the end of this year or early next year for Capacity Commitment Period June 2015. | 06.01.2015 | XLTX | CSV | |
View Archived Status at the foot of this page |
|||||
SP_PROJECTEDSHAREICR – Projected Share – Installed Capacity Requirement Report – Rev 0SP_PROJECTEDSHAREICR_<customer id>_<commitment period begin>_<version>.CSV |
|
REPORT COLUMN |
DESCRIPTION |
Tab 1 (Capacity Zone) |
|
Capacity Zone ID |
Numerical identifier for Capacity Zone in which the asset is electrically connected through a Load Zone |
Capacity Zone Name |
Name of Capacity Zone in which the asset is electrically connected through a Load Zone |
Capacity Zone Projected ICR |
Projected Share of Installed Capacity Requirement for Capacity Zone (MW). |
Customer Share of Capacity Zone Projected ICR |
Customer’s Projected Share of Installed Capacity Requirement for Capacity Zone (MW). |
Capacity Zone Peak Contributions |
The total Peak Contributions of all load and Dispatchable Asset Related Demand assets in the Capacity Zone for the subject Capacity Commitment Period. |
Tab 2 (Load) |
|
Asset ID |
Numerical identifier for the asset (Load asset or Asset Related Demand). |
Asset Name |
Name of the asset. |
Asset Type |
Type of asset (Load or Asset Related Demand). |
Capacity Zone ID |
Numerical identifier for Capacity Zone in which the asset is electrically connected through a Load Zone |
Capacity Zone Name |
Name of Capacity Zone, in which the asset is electrically connected through a Load Zone |
Peak Contribution MW |
Load Asset's contribution to peak day and hour of demand for the associated Capacity Zone (as of reference date*). |
Ownership Share |
A right or obligation to a percentage share of all Credits or Charges associated with Load asset (as of reference date*). |
Customer Share of Peak Contribution MW |
Customer's Share of Load Asset's contribution to peak day and hour of demand for the associated Capacity Zone (as of reference date*). |
| Note: The Capacity Zone Projected ICR values are for determining the total quantity of capacity that a load serving entity may designate for self-supply only and calculated pursuant to ISO-NE Market Rules and Manuals. The Capacity Zone Projected ICR values shown in this report are based on preliminary ICR values for the subject Capacity Commitment Period and will not necessarily be the same as those used when determining a Market Participant’s actual capacity requirements during the Capacity Commitment Period. | |
| *Reference date is the first day of the month prior to the report issuance date. | |
Archived Status |
||
Report Name |
Change Summary |
Effective Date |
| sp_projectedshareicr | Existing. | 06.01.2010 |